adding 2 switches to existing stack of MS425-32

I have a core of 2 MS425-32 in a stack using the 40 gig QSFP ports.

 

I want to add 2 more to the stack over SMF.  Should be supported on this model.

 

I can't have existing stack problems since it is running Aggrs and is the core of my network.

 

What is the procedure to keep current stack running and ad the 2 switches to it without downtime.

 

My thoughts from Cisco catalyst side is connect added switch while powered off.

 

It should get added to running stack? No problems?

 

I have the switches to be added already configured to use the QSFP ports as stacking ports.

 

Please let me know of any gotchas.

Thanks,

Greg

2 Replies 2
DarrenOC
Kind of a big deal
Kind of a big deal

Are you able to perform this during an agreed outage window just to cover yourself?

 

Varied experiences reported here:

 

https://community.meraki.com/t5/Switching/Adding-a-switch-to-an-existing-stack/m-p/22615

Darren OConnor | doconnor@resalire.co.uk
https://www.linkedin.com/in/darrenoconnor/

I'm not an employee of Cisco/Meraki. My posts are based on Meraki best practice and what has worked for me in the field.
alemabrahao
Kind of a big deal

Here is all the steps: https://documentation.meraki.com/MS/Stacking/Switch_Stacks#Adding_a_new_member_to_the_stack

I am not a Cisco Meraki employee. My suggestions are based on documentation of Meraki best practices and day-to-day experience.

Please, if this post was useful, leave your kudos and mark it as solved.
Get notified when there are additional replies to this discussion.
Welcome to the Meraki Community!
To start contributing, simply sign in with your Cisco ID. If you don't yet have a Cisco ID, you can sign up.
Labels