It seems I may be the nay-sayer here. I've done a handful of Meraki stacks now, and I've yet to have an installation that really went smooth.
I did a project with a single hotel, having 6 stacks, one on each floor.
Each took a good 1-1,5 hour setting up, by redoing the stacks multiple times, and having to remove my pre-configured stack in the dashboard.
I set up the main stack first, and from this in a star topology to each floor stack. They are connected to the main stack by fiber.
I followed the procedure as described in the video below, and still went south.
Just yesterday I was booked to add another switch to the main stack at the same customer. Two hours later, I was done, after spending the first hour, getting it to sign in on the Cloud.