There is 600 Sites. I can't double the routing table by adding a management subnet.
There is already going to be a heap of automation and scripting. In the end, all a person will do is put in the ADP Site code and serial numbers, and everything else will be automated.
Scripts will create the network using the ADP Code, name the devices, reach out to IPAM to find subnet located with ADP Code and configure the devices for the LAN IP info. It will also reach out to TEMS to get WAN IP address info and try to apply it to the device. From there, it will also reach out to ISE to add the devices that are needed. We are going to be adding cameras, so I will need to add them to ISE as well for MAB.
We will have 12 months to get this all done for 600+ sites. I will have entry level provisioning engineers doing most of the work, and by the end of Q1, I will have to shift back to DC work with firewalls while the other guys continue running with this.