Maybe, maybe not. Depends on @BobHarrison's goals.
If @BobHarrison's main intent is to remove 17 AP licenses from the source/original Org he could go the route of:
- Create a "license graveyard" or "dummy" destination Org
- Move 17 MR licenses from the source Org to the destination Org (as long as they're not expired and meet the requirements in the doc).
As the doc mentions (and the warning in dashboard when you perform the move) it can and typically would reduce the remaining co-term time as you're removing license "value" from the source Org.
This would put @BobHarrison's Org at 17 MRs and any newly added licenses will now only be blended with what's present in the source Org. Otherwise as mentioned the only time you could change license quantities would be using a Renewal process.
All of that said if your Org only has around a year remaining and you're planning to add a switch in that time it might just be easier to add the switch (license) and then when the Org is up for renewal right size/adjust the AP count. Adjusting the license count to 17 now likely will have very little effect to the co-term date and might be more work than it's worth.
@BobHarrison does that help? Or just confuse things more? Hopefully it helped 😀
Feel free to PM me if you want to discuss it further.
Cheers
Ryan If you found this post helpful, please give it
Kudos. If my answer solves your problem please click
Accept as Solution so others can benefit from it.