We have 2 Meraki MS-425s that are stacked physically via the 40GB Stacking ports on the front. We have a Nutanix (hyper-converged) cluster cross connected to both switches. We have a total of 4 10GB aggregated (2 per sw) connections going north bound. Originally we physically stacked the switches because we were using L3 Routing. We are no longer using L3 routing. Further, we need to be able to upgrade these switches one at a time. If we upgrade the MS425 in a stacked configuration they update almost simultaneously hence we will drop storage (bad things happen). We have had to have Meraki manually "PIN" the upgrades and kick off the upgrade one switch at time in order to upgrade the FW. Is there an easy way out of this besides a long maintenance window (complete shutdown of of the cluster and MS425's)?