Why a 2 stage process to physical stacking?

Solved
AndyM
Here to help

Why a 2 stage process to physical stacking?

Hello community, I am planning a deployment of stacked switches. According to documentation the tasks include.

 

  1. Add switches to dashboard. Do not configure the stack in Dashboard yet.
  2. Connect each switch with individual uplinks to bring them both online and ensure they can check in with the Meraki Dashboard.
  3. Download the latest firmware build using the Firmware etc
  4. With all switches powered off and links disconnected, connect the switches together via stacking cables.
  5. Connect one uplink for the entire switch stack. 
  6. Power on all the switches, then wait several minutes for them to download the latest firmware and updates from Dashboard. The switches may reboot during this process.
  7. Navigate to Switch > Monitor > Switch stacks.
  8. Configure the switch stack in Dashboard.

 

The documented process means that I cannot pre-provision them in the dashboard.

 

When deploying a Meraki solution, I have always pre-provisioned everything, and the installers only need to plug everything in as directed by my instructions. Usually completed whilst I am asleep.

 

So, to my question.

 

Has anyone out there just pre-provisioned stacks in the dashboard (without steps  1-5) then connected them to the network. If so, what goes wrong that means that I need to do it according to the documentation.

 

Thanks Andy

1 Accepted Solution
cmr
Kind of a big deal
Kind of a big deal

We have done several physical stacks and as @PhilipDAth said, as long as you power them up first on their own before physically stacking them, you will be okay.  We have followed the following process:

 

  1. Create the stack in the dashboard by adding the serial numbers
  2. Plug in switches on their own with internet access and leave for a few hours
  3. Power off switches
  4. Install one of the switches in destination and power up, connect devices if needed, to free up space in panel if replacing other switches etc.
  5. Install second switch in destination and connect stacking cable(s), then power up
  6. Add third etc. if required.

As long as you aren't using layer 3 features (we aren't), then it all works fine and there are no connectivity issues for clients, switch reboots etc.  We did this with 10.x firmware but haven't added any more yet since moving to 11.x

If my answer solves your problem please click Accept as Solution so others can benefit from it.

View solution in original post

10 Replies 10
PhilipDAth
Kind of a big deal
Kind of a big deal

The important but is you need to get them all online first and let the software upgrade.

 

In the earlier firmware images like 9.x the switches could crash or lockup.  Not sure how the modern firmware versions go - but you can't tell what firmware version they ship with.

 

We tend to do bring our switches online and upgrade the firmware at least a day before we install them on site. 

That first upgrade can take a long time.  40 minutes sometimes.

 

Also don't watch them.  Just walk away and do something else.  Otherwise you'll start thinking something is wrong and power cycle then which starts the whole process again. 

AndyM
Here to help

I had a sneaking suspicion that might be the experience of the community. I hope someone else has a different answer which makes my life easier. But I bet everyone says the same thing. Thanks @PhilipDAth  for the detail about 40 minutes, as I think by then I would have assumed things were not going well.

Uberseehandel
Kind of a big deal

It is not just Meraki - it is all network equipment - start upgrading and go and have a coffee out of the building. Or an ice-cream.

Robin St.Clair | Principal, Caithness Analytics | @uberseehandel
AndyM
Here to help

@Uberseehandel , It was more why boot it unstacked first, then let it upgrade the firmware, and then stack them together. I'd rather stack it, and boot it, and then let it upgrade itself whilst it is in a stack. But Meraki are quite clear in that they highlight boot it unstacked and don't configure in the dashboard. Then once upgraded stack it and configure it.

 

I suppose if you stacked two devices with incompatible FW, then they may not stack, and one or more may not upgrade.

 

@Nash I've rolled out 500+ Meraki devices pre-configring the lot in the dashboard, and got the installer to plug them in as documented, and only had issues when the wrong ports were selected. I found it more efficient. Those however were not stacked, so I have been backed into a corner.

Nash
Kind of a big deal

@AndyM I understand. I'm specifically talking about physical stacks here. It's not my favorite either.

cmr
Kind of a big deal
Kind of a big deal

We have done several physical stacks and as @PhilipDAth said, as long as you power them up first on their own before physically stacking them, you will be okay.  We have followed the following process:

 

  1. Create the stack in the dashboard by adding the serial numbers
  2. Plug in switches on their own with internet access and leave for a few hours
  3. Power off switches
  4. Install one of the switches in destination and power up, connect devices if needed, to free up space in panel if replacing other switches etc.
  5. Install second switch in destination and connect stacking cable(s), then power up
  6. Add third etc. if required.

As long as you aren't using layer 3 features (we aren't), then it all works fine and there are no connectivity issues for clients, switch reboots etc.  We did this with 10.x firmware but haven't added any more yet since moving to 11.x

If my answer solves your problem please click Accept as Solution so others can benefit from it.
AndyM
Here to help

@cmr That sounds a bit more hopeful, at least I could pre-configure them.

cmr
Kind of a big deal
Kind of a big deal

@AndyM did you have any luck with the process we followed?

If my answer solves your problem please click Accept as Solution so others can benefit from it.
AndyM
Here to help

@cmr I'm at the low level design/ building instructions phase of the design. So it will be while before I get my hands on the hardware.

Nash
Kind of a big deal

@AndyM Upgrade does sometimes take longer than you'd like. My team's practice is to setup devices for their initial load and then ignore them for 1-2 hours. If the lights or dashboard status are unhappy after then, then we've got a problem. But it's switches. I haven't met a good switch yet that doesn't sometimes take an age or three to update from the shipped firmware to modern firmware.

 

For stacks, we usually follow that process you described... in our office. Once it's ready to go and we've labeled each switch with its intended stacking order, then it can be sent off to the installer. We don't drop ship them to site and cross our fingers.

Get notified when there are additional replies to this discussion.
Welcome to the Meraki Community!
To start contributing, simply sign in with your Cisco account. If you don't yet have a Cisco account, you can sign up.
Labels