Not sure why 3 downlinks are needed….seems a bit overkill or over engineered.
Too many redundant paths likely intended for a failover situation but the errors seem to be the redundant paths (3 downlinks).
If it were my network to remedy, each switch would have only two downlinks with all root traffic from SW00.
SW01 and SW02 would be one alt path (loop guard)
SW03 and SW04 would be one alt path (loop guard)
I would remove the link between SW02 and SW03.
I would remove the link between SW01 and SW04.
Thanks for sharing the topology to better understand.
That would be my suggestion/recommendation.