I recently upgraded a network with six switches using the stages upgrades option as below:
![cmr_0-1581419774531.png cmr_0-1581419774531.png](https://community.meraki.com/t5/image/serverpage/image-id/11611i3A01F17038711DE8/image-size/medium?v=v2&px=400)
The actual device reboots were:
09:26 (26 minutes after schedule)
09:31 (1 minute after schedule)
10:26 (26 minutes after schedule)
10:56 (26 minutes after schedule)
The first device is a 220, the second a 120, the third a stack of a 225 and 210 and the fourth a stack of a 225 and a 210.
Probably worth bearing in mind when using this feature that the 2xx switches all reboot 26 minutes into the window but the 1xx switch only waited 1 minute!