FLexible Stacking Question ?

Mac1
Comes here often

FLexible Stacking Question ?

hello all. In this video he shows you how to configure flexible stacking. 

 

He first powers on both switches with with separate uplinks then configures the stacking ports on each switch and adds the stack cables without powering off the switches, unlike regular  stacking.

At what point can you remove ONE  of the uplinks as he never does that in the video?

 

Do you remove the uplink BEFORE you start configuring the stack  ports or after?

 

Flexible Stacking 

2 REPLIES 2
ww
Kind of a big deal
Kind of a big deal

After you press provision  stack i would wait like 10 minutes and if dashboard reports no issues .  Then remove it.

Mac1
Comes here often

Thanks, i'll let you know how i get on next week.b

Get notified when there are additional replies to this discussion.
Welcome to the Meraki Community!
To start contributing, simply sign in with your Cisco account. If you don't yet have a Cisco account, you can sign up.
Labels